PROJECT DETAILS
Place of application: Oil Field Damborice
Used Cleaning Technology: Downhole equipment cleaning (rod string and tubing) with DIR-X down the tubing (interrupted production – unseated pump)
Over the years 2008 to 2021 were cleaned 10 wells.
Wells Parameters
Wells: depth 1700 – 1800 m, reservoir temperature 48°C, pump setting depths 1200-1400 m, there were a problem with paraffin deposits
Standard cleaning method (3 – 5 day workover / Intervention): pull the sucker rod pump and tubing out of the hole, cleaning with the steam from paraffin / asphaltene at the surface, casing cleaning with the scraper and hot oiling.
Cleaning process – Heating up the production tubing, subsurface rod pump and rod string
Mixture quantity: 2,4 m3
Cleaning time: 3 hours
Dewaxing the downhole completion (subsurface rod pump, rod string and production tubing) with the use of Termo-U.
Process:
- unseat the pump,
- check the pump unseating with the oil circulation down the tubing,
- pump the Termo-U / 2,4 m3 / down the tubing,
- after the reaction brake / 10 minutes / , pump 3 m3 of oil down the tubing to wash out the spent Termo-U with melted asphaltene/paraffin to the annulus,
- seat the pump and put the pumping unit into the operation
Result of Cleaning
Circulation pressure after cleaning was much lower. After 3 hours well cleaning by TERMO-U system, was well production restored to designed Capacity and Nominal Operation conditions in very short time and with lower costs.

Nr.1 Rods after cleaning by TERMO-U